U.S. nonresidential development backlog rebounded in August as a report percentage of Related Developers and Contractors contributors reported having knowledge heart paintings underneath contract, ABC reported Sept. 15.
ABC’s Development Backlog Indicator rose to eight.5 months from 8.0 months in July, returning to its August 2025 degree. The effects are in response to an ABC member survey carried out Aug. 20 to Sept. 4.

Infrastructure backlog jumped 1.2 months in August to ten months, whilst heavy business backlog fell to eight.3 months and stays 2.7 months under its year-ago degree. Click on to magnify.
Chart courtesy Related Developers and Contractors
About one in six ABC contributors is lately underneath contract to accomplish knowledge heart paintings, the perfect percentage the affiliation has recorded. Contractors operating on knowledge facilities reported a 9.9-month backlog, when put next with 8.3 months for contractors with out such paintings.
“Knowledge facilities proceed to stay contractors busy whilst process softens in different segments,” ABC Leader Economist Anirban Basu stated. He stated the narrowing backlog hole between contractors with and with out knowledge heart paintings seems to replicate extra corporations securing knowledge heart initiatives, reasonably than a broader marketplace shift.
Infrastructure backlog used to be perfect a few of the 3 sectors at 10 months, up from 8.8 months in July however down from 11.2 months a 12 months previous. Industrial and institutional backlog larger to eight.5 months from 8.0 months in July. Heavy business backlog fell to eight.3 months from 9.2 months and is down from 11 months in August 2025.
ABC’s Development Self belief Index for gross sales rose to 62.0 in August from 61.2 in July, whilst the profit-margin studying edged as much as 52.9 from 52.7. Staffing self assurance fell to 59.5 from 62.3. All 3 remained above 50, indicating expectancies for expansion over the following six months.
“The percentage of contractors that intend to chop their staffing ranges over the following six months rose to twelve.3% in August, probably the most in any month since December,” Basu stated. He added that extra contractors discussed exertions shortages with out being brought on and pointed to development process openings at a close to two-year prime.
Searching for fast solutions on development and engineering subjects?
Check out Ask ENR, our new sensible AI seek instrument.
Ask ENR →
ENR reported Sept. 3 {that a} separate AGC-NCCER body of workers survey discovered 28% of respondents had carried out knowledge heart paintings all through the former 12 months. Amongst corporations reporting body of workers results, 58% cited better pageant for experienced employees and 49% larger salary drive.
Development corporations added 22,000 jobs in August, whilst the business’s unemployment charge fell to a few.1%, the bottom for any month in 26 years of to be had knowledge, in step with an AGC research of federal employment knowledge.