Canadian infrequent earth developer Aclara Assets mentioned Oct. 13 that it has finished elementary engineering for a deliberate heavy infrequent earth separation facility in southwest Louisiana, a $494-million facility that has scaled up its projected processing functions in fresh months.
Referred to as Mission Dynamo, the ability is about for an roughly 82-acre web site on the Port of Vinton, about 30 miles west of Lake Charles, L. a.., the place Aclara intends to procedure rare-earth carbonate from its mining initiatives in Brazil and Chile into person high-purity rare-earth oxides.

Aclara is trying out Mission Dynamo’s separation procedure and coaching team of workers at its Virginia Tech facility prior to advertisement operations start in Louisiana. Click on to amplify.
Photograph courtesy Aclara Assets
The revised Magnificence 3 estimate below AACE Global requirements is set 78% upper than the $277-million Magnificence 5 conceptual estimate Aclara disclosed in an April scoping find out about. The brand new estimate follows of completion of elementary engineering and contains an expanded challenge scope, together with further processing capability and 3 new separation circuits.
Mississauga, Ontario-based engineering company Hatch carried out the elemental engineering paintings.
“The paintings performed in conjunction with Hatch has materially complex the definition of the ability, from procedure design and gear variety via procurement making plans and constructability, offering a robust basis for the development section,” Aclara Leader Running Officer Hugh Broadhurst mentioned within the announcement.
Broadhurst advised ENR in an Oct. 14 e-mail that the upper estimate displays each greater and extra processing apparatus. Separation capability higher to deal with feed from Aclara’s mining initiatives in Brazil and Chile, elevating deliberate dysprosium and terbium capability through 42%, whilst including gadolinium, samarium and yttrium oxides calls for further separation apparatus.
“In abstract, the rise essentially associated with the higher processing capability of 157% extra oxide capability but additionally contains the upper stage of engineering definition transferring from a Magnificence 5 to Magnificence 3 estimate,” Broadhurst says.
Searching for fast solutions on development and engineering subjects?
Check out Ask ENR, our new good AI seek software.
Ask ENR →
Web site preparation is focused to start out within the first quarter of 2027, topic to financing and different stipulations, with development of completion deliberate for the second one part of 2028.
Engineering Advances Towards Building
Providers have supplied quotations for all primary apparatus programs, in line with Aclara, which expects to obtain about 86% of kit programs and all electric programs within the U.S.

Mission Dynamo could be constructed on the Port of Vinton in southwest Louisiana, the place Aclara plans a $494-million infrequent earth separation facility. Click on to amplify.
Screengrab courtesy Port of Vinton/ENR
Aclara has an engineering, procurement and development control contractor variety procedure underway, Broadhurst tells ENR. Choice of the EPCM company and different contractors stays in development.
The Lake Charles area supplies a group of workers skilled in petrochemical and refining operations, Aclara says. The web site additionally provides freeway get entry to, connectivity to the Gulf Intracoastal Waterway, proximity to chlor-alkali manufacturers supplying procedure reagents and area for a proposed downstream metals and alloys facility.
The expanded plant is now designed to provide about 200 tonnes of dysprosium oxide and 35 tonnes of terbium oxide once a year, in conjunction with yttrium, gadolinium and samarium oxides from the 3 newly added separation circuits.
Entergy Louisiana is predicted to offer 34.5-kV electric provider to the ability, which will require lower than 5 MW, in line with Aclara. The developer says Entergy has showed roughly 6 MW of to be had capability and is making an investment in infrastructure to toughen energy supply on the Port of Vinton.
Sequential extraction, scrubbing and stripping circuits would shape the core of the plant’s solvent-extraction procedure, in line with Aclara. An indication facility on the Virginia Tech Company Analysis Heart in Blacksburg, Va., is producing running knowledge to refine the method prior to commercial-scale deployment and teach engineers, chemists and operators. The ability has produced neodymium-praseodymium oxide to its focused specification and is being expanded to check the 3 further circuits, the corporate says.
RELATED
Fluor Wins Uncommon Earths Plant Mission as US, Australia Markets Increase
Financing Stays a Hurdle
Aclara won a small-source air allow from the Louisiana Dept. of Environmental High quality in September. Broadhurst tells ENR the corporate considers it the vital air allow had to start development and says final commonplace construction lets in don’t seem to be anticipated to lengthen web site preparation.
Financing has now not been finished. The Export-Import Financial institution of america issued Aclara a nonbinding letter of passion Sept. 4 indicating it will imagine as much as $750 million in financing for the corporate’s broader deliberate Louisiana separation, metals and alloys platform. Aclara is getting ready a proper software, and any financing stays topic to EXIM due diligence, underwriting and approvals.
“With the air allow from the Louisiana Division of Environmental High quality secured and a possible financing pathway with EXIM, the Mission is situated to transport towards execution,” Broadhurst mentioned within the information unencumber. “We at the moment are inquisitive about starting web site preparation actions in Q1 2027.”