HG Development has been ordered to pay nearly £1m to a residential developer, after a pass judgement on rejected its argument that it were granted extra extension of time than had in reality been agreed.
The contractor was once construction a 153-room resort and 9 new construct residences for Clerkenwell Way of life UK in Eyre Boulevard Hill, Clerkenwell, east London, the place paintings began in December 2021 and was once because of be finished in June 2023.
Alternatively, its development was once hit by way of a sequence of problems together with Covid, beneath flooring obstructions, shipping moves, deficient climate stipulations and issues of subject matter sourcing and supply.
Of completion of the residential segment was once revised to August 2023 and the resort for the next month.
After the resort was once completed in October 2024 and the residential component of the mission was once finished in February 2025, Clerkenwell attempted to get better £1.2m in liquidated damages by the use of an adjudication.
Adjudicator Matthew Molloy determined most commonly within the shopper’s favour previous this 12 months, awarding it £955,943.43.
HG appealed the verdict, arguing the adjudicator had now not considered that additional extension of instances were agreed with Avison Younger, appearing for the buyer, by way of electronic mail in February 2023.
Mrs Justice Jefford, on the Generation and Development Courtroom, stated the contractor didn’t make a constant case to the adjudicator that of entirety dates mentioned within the electronic mail have been key to its case concerning the programme’s baseline.
She stated the case it offered to the adjudicator relied at the extend brought about by way of Covid, which was once now not discussed within the February 2023 extension of time case.
The pass judgement on stated that whilst the contractor did talk about an extension with the guide on the time, the dialog was once about being prepared to grant an extension relatively than in reality legally agreeing to take action.
Two months previous, Avison Younger had instructed HG if it made an software for an extension it might then be granted, and she or he stated this was once nonetheless a part of an ongoing dialogue.
“The events have been agreeing how they’d function the contractual mechanism and now not that they’d input into some free-standing and binding settlement to revise the of entirety dates,” she stated.
Whilst the e-mail mentioned proposals to separate sure additional prices, agreeing to evaluate ultimate quantities, it additionally referred to an settlement “in concept” to award an extra extension of time as soon as an addendum birthday celebration wall award was once agreed and the whole have an effect on at the programme assessed.
She stated this confirmed the e-mail was once now not meant to be binding, and despite the fact that it was once, it was once now not written obviously sufficient to be enforceable.
Mrs Justice Jefford ordered HG Development to pay Clerkenwell £955,943.43 and the adjudicator’s charges.




