A building corporate has been fined £100,000 after a metal-fixer used to be significantly injured when a newly constructed blockwork wall collapsed at a web site in Poole.
Matrod Frampton Restricted pleaded in charge at Bristol Magistrates’ Courtroom after the incident left 69-year-old Patrick Grant with life-changing accidents.
The court docket heard how a breeze block wall were back-filled too early, ahead of the mortar had correctly set. The wall collapsed whilst Mr Grant used to be operating within reach, crushing him towards the concrete flooring of the excavation.
The incident took place on 19th August 2022 on the corporate’s web site on Outdated Coast Guard’s Highway, Poole. Mr Grant and two colleagues had began paintings on the decrease stage of the excavation when the wall on the north finish gave manner at round 8.30am.
Emergency products and services attended the scene, however there used to be no emergency rescue plan in position. Using an volatile ladder to get right of entry to the deep excavation behind schedule rescue efforts, and Mr Grant needed to be hoisted out by means of the fireplace and rescue provider ahead of being airlifted to clinic.
An investigation by means of the Well being & Protection Government (HSE) discovered that Matrod Frampton had failed to correctly assess a foreseeable chance related to brief works on web site.

The investigation known that there used to be no brief works design for the blockwork wall, nor for every other brief paintings buildings on the web site. The corporate had didn’t appoint both a short lived works coordinator or a short lived works manager, in spite of this being highlighted as a significant fear in a security document issued 8 days ahead of the incident.
With out a brief works process in position, groundworkers backfilled the wall upfront, main at once to its cave in.
Matrod Frampton Restricted, of Riverside Park, Wimborne, Dorset, pleaded in charge to breaching Laws 13(1) and 19(1) of the Development (Design and Control) Laws 2015. It used to be fined £100,000 and ordered to pay £8,242 in prices and a £2,000 sufferer surcharge at Bristol Magistrates’ Courtroom on 5th December 2025.
HSE inspector Alexander Ashen stated after the listening to: “The right kind design and execution of brief works is an crucial component of chance prevention in building. This incident illustrates what can occur when brief works aren’t correctly organised.
“Matrod Frampton Restricted is a longtime building corporate, and a short lived works process must had been carried out as an issue after all. The truth that the corporate’s personal well being and protection experts raised this factor 8 days ahead of the incident makes this wholly avoidable match all of the extra tragic.”
The collapsed wall the place Patrick Grant used to be operating at the excavation
Were given a tale? E mail information@theconstructionindex.co.united kingdom
![The collapsed wall where Patrick Grant was working on the excavation [HSE]](https://www.theconstructionindex.co.uk/img-cache/cd0a581d078a6d1818af55079232aeb3/750x500_top_1765957495_matrod-wall.jpg)