Rhode Island can construct a brand new bridge with out federal investment, consistent with State Transportation Director Peter Alviti. Additionally, URI’s athletic box renovations, together with Meade Stadium and a brand new observe, will boost up in 2025, with investment coming from the state price range and ongoing fundraising efforts.
Wed February 26, 2025 – Northeast Version

RIDOT picture
Even supposing the government witholds loads of thousands and thousands of federal bucks in the past promised to Rhode Island, the state may have greater than sufficient cash to construct a brand new westbound Washington Bridge
Even supposing the government witholds loads of thousands and thousands of federal bucks in the past promised to Rhode Island, the state may have greater than sufficient cash to construct a brand new westbound Washington Bridge, state Transportation Director Peter Alviti instructed a joint Area-Senate Oversight listening to on the Statehouse in Feb.
Alviti mentioned greater than $600 million has been allotted for the bridge and a chain of enhancements alongside Interstate 95 in Windfall, R.I., and that the cash does now not fall into the kinds being limited via the White Area.
In keeping with The Public’s Radio in Windfall, Alviti mentioned the Rhode Island Division of Transportation (RIDOT) stays in common touch with federal transportation officers about seeking to spur the discharge of the finances.
“However of their absence, now we have the investment in position throughout the GARVEE debt [capacity],” he mentioned, relating to a type of borrowing for transit initiatives referred to as Grant Anticipation Earnings Automobile Bonds, “and different resources that I defined for you so that you can construct the bridge. So, we are transferring forward.”
There have been few different contemporary revelations all over the virtually three-hour listening to on Feb. 13, 2025.
State Sen. Mark McKenney and chair of the Senate Committee on Laws, Govt Ethics and Oversight, famous on the assembly’s outset that complaints over the Washington Bridge’s situation being led via Lawyer Common Peter Neronha restricted Alviti’s skill to talk about the roots of the bridge disaster and why it took place.
The westbound Washington Bridge was once unexpectedly closed on an emergency foundation in December 2023.
Nonetheless, lawmakers pressed Alviti to reply to when the brand new westbound bridge might be entire and what kind of it’ll price.
The Public’s Radio reported that Alviti spoke back via pronouncing what he and Gov. Dan McKee have mentioned prior to: {that a} ultimate contractor for the challenge is slated to be decided on in June 2025 and that the price and timeline might be detailed at that time.
State Rep. Pat Serpa, chair of the Area Oversight Committee, prefaced her wondering of Alviti via lambasting RIDOT.
“My greatest worry is that Rhode Islanders have misplaced their religion within the Division of Transportation and that hasn’t been mounted but and I do not understand how we are going to repair that,” she mentioned, pointing to how the state has but to choose a contractor greater than a yr after the ultimate of the bridge and after an preliminary RFP attracted no bids.
Whilst Alviti touted enhancements in shuttle occasions at the bridge, Rep. June Speakman added that she continues to listen to from pissed off constituents.
“The East Bay citizens have moved of their processing of the placement from form of anger and confusion to resignation concerning the visitors and now we pay attention much more concerning the issues of the tension at the [eastbound] bridge, which is wearing visitors east and west, as a result of we spend such a lot time on it,” she mentioned.
Whilst the set up of tracking apparatus at the eastbound bridge is handiest partly entire, Alviti defined that the construction is being monitored each day and will safely elevate its greater visitors.
As well as, he instructed lawmakers that RIDOT has progressed loads of bridges lately and famous the alternative of the westbound Washington Bridge is transferring extra temporarily than the rebuilding of the Francis Scott Key Bridge in Maryland.
“I am more than happy, let me inform you, with the development and the trouble and I could not be extra pleased with those other people in the back of me,” he mentioned, relating to RIDOT staffers, “on the degree of effort and the type of effects that they’ve been getting.”
“I have no idea what development you have got accomplished,” Alviti endured. “I have constructed 290 bridges and let me inform you, this one goes quicker and higher throughout the procurement procedure, the subsurface explorations, the demolition, than any challenge this state has ever observed even prior to my time and we intend on holding it that manner.”
URI Athletic Box Renovations Prone to Boost up in 2025
Ongoing renovations to the College of Rhode Island’s athletic fields in Kingston are anticipated to select up later this yr, with formal development at the college’s new outside observe and box anticipated to begin this summer season, Thorr Bjorn, URI’s Director of Athletics, lately instructed Windfall Industry Information (PBN) for a Feb. 25, 2025 article.
As well as, Bjorn mentioned development on Meade Stadium, house to URI’s soccer and new girls’s lacrosse techniques, is anticipated to begin in November 2025 on the conclusion of subsequent soccer season. The stadium renovation is slated to take 18 months, he mentioned, whilst development of the observe will start in a couple of yr.
Due to this fact, the soccer group must play its 2026 house time table at an alternate web site, Bjorn mentioned, prior to returning to Meade within the fall of 2027. He mentioned URI is looking for a brief house facility for soccer, with hopes of getting “a truly excellent plan in position” via summer season 2025.
When requested if the brand new Stadium at Tidewater Touchdown in Pawtucket — set to open in Would possibly 2025 — is an opportunity for URI soccer, Bjorn mentioned it might be “a super possibility” however would rely at the utilization price.
“There may be without a doubt nice other people there and it is a nice facility,” he instructed PBN. “We need to determine what makes essentially the most monetary sense [for us] and [the most sense for fans].”
Bjorn additionally mentioned he hopes girls’s lacrosse may also be performed inside of Meade whilst development is ongoing, however added, “We will see.”
Each Meade Stadium and the brand new outside observe are the centerpieces of URI’s $82 million renovations to more than one athletic fields and growing older amenities. The football and softball fields, in addition to underground infrastructure at Tootell Aquatic Middle, are also being upgraded.
New synthetic turf was once put in on the baseball box fall 2024, PBN famous. The design paintings for Meade and the observe was once accomplished first, given their price and dimension, Bjorn mentioned, and the preliminary designs for the opposite fields will confidently be entire “within the close to long term.”
The college gained $65.8 million in Rhode Island’s 2024 fiscal yr price range to fund many of the initiative. In October 2023, URI introduced a $20 million fundraising marketing campaign to near the monetary hole for the challenge.
Bjorn mentioned the college remains to be fundraising the general $16 million to complete the challenge. Conversations between URI athletics and donors are “going neatly,” he mentioned, however bodily designs appearing the completed challenge will most probably assist drum up extra enthusiasm and fiscal contributions.