A document as of late from the Nationwide Audit Workplace (NAO), the federal government spending watchdog, says that the present Labour govt has put the brand new clinic programme in England on less attackable footing with its rescheduling however RAAC-affected constructions will leave out the 2030 alternative time limit.
Final yr’s reset of the brand new clinic programme (NHP) has given it a extra reasonable timetable, the NAO says. Alternatively alternative schemes for hospitals constructed with strengthened aerated autoclaved concrete (RAAC) were given too tight a development agenda and with little contingency within the subsequent 5 years, there are vital supply dangers.
The NAO has printed an replace to its 2023 document at the new clinic programme at the again of the brand new govt resetting the programme. The reset covers 41 clinic schemes throughout England, starting from entire new constructions to primary refurbishments, and will likely be performed in 4 waves over the following two decades. An extra 5 schemes had been already entire and open when the programme used to be reset in January 2025.
The general hospitals are anticipated to be finished in 2045-46.
Executive has allotted round £2bn a yr to the programme from 2025-26 to 2029-30, emerging to £3bn a yr from 2030-31. An estimated general capital investment of round £56bn will likely be required. Extra reasonable making plans assumptions imply that it is a £33.8bn build up at the capital investment proposed in 2023. A £12bn contingency (21%) has been in-built to replicate inflation, marketplace pressures, engineering demanding situations and environmental necessities.
An unbiased 2022 document beneficial that the seven hospitals predominantly constructed from RAAC must get replaced through 2030 at the newest. Whilst those are actually prioritised within the revised NHP, they are going to now not get replaced through that date, the NAO says. An extra document printed in December 2025 concluded that, with mitigations and sustained upkeep, those hospitals can stay operational past 2030. Alternatively, those hospitals will face vital prices and operational dangers together with protection dangers to sufferers. Through 2025, the seven hospitals had required greater than £500m of funding to stop structural failure.
Trusts whose new hospitals or refurbishments will open later will face further prices to deal with aging constructions for longer – estimated through govt at between £100m and £140m a yr.
The programme plans to introduce a extra standardised technique to design and development. The brand new “Medical institution 2.0” design could also be operating to toughen potency and affected person care; this must come with every affected person having their very own room, shorter strolling distances for group of workers, paperless affected person information, and applied sciences similar to infrared sensors to alert group of workers when a affected person falls.
Because the new plan and investment commitments had been introduced, the programme has had expressions of pastime from greater than 20 doable primary contractors and is taking 16 pre-qualified bidders thru ‘aggressive discussion’ to assist expand answers and technical specs previous to filing ultimate tenders.
Nowadays’s NAO document warns that the development agenda over the following couple of years is difficult as clinic schemes adapt to the brand new method. If early schemes fall in the back of, there are dangers of supply dates slipping and paintings might bunch up later. This is able to result in finances pressures on later clinic waves.
The programme additionally continues to stand group of workers demanding situations. As of November 2025, NHP had 138 vacancies out of 357 posts, a emptiness charge of 39% for public sector roles with gaps in virtual, criminal, industrial, challenge supply and technical roles.
The NAO has a number of suggestions for the Division of Well being & Social Care (DHSC) and its new clinic programme staff. Those come with:
- deal with rigorous programme oversight to stay supply on target, be told classes between schemes and reply to adjustments in healthcare wishes.
- get the Medical institution 2.0 design proper through permitting sufficient time for trying out and making sure sturdy enter from agree with group of workers and leaders.
- toughen long run value estimates and align supply and investment profiles, weighing any acceleration of schemes towards supply dangers, business capability and value pressures.
- percentage the long run call for type broadly around the NHS and govt, making sure constant native determination making and steady type refinement.
- observe the shift to group care carefully to steer clear of underneath sized hospitals, refining call for assumptions and growing transparent contingency plans around the wider well being machine.
Gareth Davies, head of the NAO, mentioned: “The reset of the brand new clinic programme offers the dep. a less attackable platform to ship long run enhancements, and its ambition to change into clinic infrastructure has actual doable equipped designs are carefully examined and programme supply is easily controlled.”
Sir Geoffrey Clifton-Brown, chair of the Space of Commons Committee of Public Accounts, mentioned: “New hospitals are desperately had to deal with the longstanding backlog of funding. “When the Committee of Public Accounts final reported at the new clinic programme in 2023, we discovered no self belief that the guarantees made within the programme had been deliverable. DHSC has since reset the programme, offering a extra reasonable supply timetable and price estimates. Present projections point out that the schemes will value £60bn in general. This represents a £33.8bn build up at the capital investment proposed in 2023. “DHSC’s extra centralised method has the facility to ship a better go back on funding, enhanced virtual generation and progressed emergency efficiency, with the longer-term investment dedication serving to to protected higher industrial pastime. Alternatively, additional delays in totally addressing crumbling RAAC in hospitals pose vital medical and price dangers, which should be addressed as a question of urgency.
“It’s crucial that DHSC maintains rigorous oversight over the programme in order that sufferers and clinicians don’t wait even longer for his or her new hospitals to be finished.”
Replace at the New Medical institution Programme is to be had by way of nao.org.united kingdom
Were given a tale? E-mail information@theconstructionindex.co.united kingdom