United Utilities has awarded Barhale 3 contracts below its £3bn Higher Rivers programme, which is geared toward making improvements to water high quality and protective over 300 miles of waterways around the northwest of England.
Barhale’s contracts – at Cheadle in Stockport, and Wheatfield Shut and Thornton in Merseyside – are designed to extend garage capability and reinforce community efficiency, serving to United Utilities meet its goal of lowering spills from hurricane overflows by means of 60% sooner than 2030.
The paintings can be delivered inside United Utilities’ AMP8 framework.
The challenge at Cheadle will see Barhale assemble a 500 cubic metre detention tank and a ten.5m-diameter, 13m-deep segmental shaft along changes to the prevailing blended sewer overflow (CSO) and upgrades to the valve and drift meter chambers.
At Wheatfield Shut, Barhale will design and construct an extra 1400 cubic metre garage centred on a 15m diameter and 13m deep segmental, caisson-built shaft and valve and drift chamber works and enhancements to the prevailing CSO. Barhale will even entire Phase 278 highways works to deal with a brand new get right of entry to path to the shaft.

At Thornton a 14m-diameter by means of 6m-high (above floor) stainless metal segmental tank will assist create an extra 1,000 cubic metres of garage. Further related works come with a brand new 4m by means of 6m (deep) rainy smartly, drift chambers, CSO changes and a brand new outfall with headwall to extend structural steadiness.
Barhale regional supervisor Nick Curtis mentioned that development new garage and maximising the headroom within the current infrastructure used to be permitting the challenge objectives to be accomplished with a discounted construct.
“It’s an absolute precedence to assist offer protection to rivers and the broader atmosphere by means of lowering spills from hurricane overflows,” he mentioned. “We’re demonstrating that it’s imaginable to take action each handing over perfect price whilst minimising intrusiveness for purchasers and communities.
“We’ve labored carefully with United Utilities to form each and every of the challenge approaches and are having a look ahead to creating our contribution to the Higher Rivers challenge.”
Final touch at Cheadle is predicted in April 2026; at Wheatfield Shut in June 2026; and at Thornton by means of March 2026.