What’s described as some of the important infrastructure initiatives within the Wrexham soccer historical past has now moved to complete structure part.
The 5,500-capacity new Kop Stand, designed by way of Populous, will building up capability at the Racecourse Floor (STōK Cae Ras) to greater than 18,000 in addition to carry stepped forward amenities
Set for finishing touch all through the 2026/27 season, it’s going to repair the stadium to a four-sided configuration and succeed in UEFA Class 4 compliance.
Representatives from Wrexham AFC, Wrexham County Borough Council, McLaren Building Midlands and North, the Welsh govt, Wrexham College and the Wrexham Gateway Partnership assembled on the Racecourse Floor (STōK Cae Ras) on 4th December to mark the beginning of major works.
Since McLaren Building’s appointment below a pre-construction services and products settlement previous this 12 months, the mission group has finished a set of enabling works to arrange the website online for complete structure. Those works have integrated setting up the early-phase compound and welfare amenities, finishing the reduced-level dig and stabilised structure platform, putting in the piling mat, relocating and upgrading hoarding, forming an everlasting secure walkway from the Wrexham Lager Stand, developing structure get entry to routes and crane platforms and beginning piling operations that can proceed into the early new 12 months.
The mission now strikes into its fundamental structure duration, with the breakout piles, casting of foundations all beginning this month and into January, and the beginning of bolstered concrete elevate cores that can reinforce the brand new structural metal body at the side of the root. Paintings may even development on interior carrier ducting, drainage and preparation of the principle flooring flooring slab.
In early 2026, slip shaped bolstered concrete cores can be built to supply steadiness for the roof construction. The metal body, which incorporates roughly 1,500 tonnes of metal together with primary long-lead tubular truss sections, is scheduled to start out emerging from early spring.

Set up of precast concrete terrace devices will practice sooner than roofing and façade works, interior fit-out and methods set up proceed thru the rest of 2026 and into 2027.
The mission group has labored to deal with the complexities of establishing a brand new stand inside a are living, operational and traditionally delicate stadium surroundings. An in depth sequencing technique has been evolved to control business actions and structure operations inside the tight website online footprint, whilst logistics making plans has been coordinated with Wrexham County Borough Council, Wrexham College and close by companies to minimise disruption.


Joel Casstles, operations director at McLaren Building Midlands and North, stated: “The groundbreaking rite marks the beginning of a thrilling part for Wrexham AFC and for the town. The size and complexity of the brand new Kop Stand are important, particularly on a historical and operational website online, however the development made so far manner we’re getting into the principle construct with self assurance.
“This stand will grow to be the stadium and ship a brand new gateway to Wrexham, which the entire group can also be happy with. We’re dedicated to making sure the mission creates native alternatives and leaves a long-lasting legacy for supporters and citizens alike.”
Wrexham AFC leader govt Michael Williamson stated: “Over the approaching months, fanatics will see the construction take form as we construct a stand that complements capability, improves amenities and secures the way forward for the STōK Cae Ras as a top-tier venue for home, global soccer and different carrying and leisure occasions.”