Mace Dragados, HS2’s major contractor for the brand new Euston station, has subcontracted utilities infrastructure works to Barhale.
Barhale has an in depth time table of utilities infrastructure works to proceed the multi-utility hall that it built all over the primary segment of works across the northern segment of the web page. This may lengthen across the south of Euston station sooner than reintegrating with the present software networks.
Barhale will design and construct a complete of: 210 metres of 1000mm (42”) diameter and 360 metres of 250mm diameter recent water diversions; 220 metres of 1500mm diameter foul water sewer diversion; 190 metres of 800mm (36”) gasoline major diversion; 180 metres of recent top voltage and 90 metres of communications cables; and a couple of localised facilitating diversions of secondary products and services.
Senior contracts supervisor Mike Faherty defined that the provider hall is going across the entrance of the present mainline teach station, via Euston Sq..
“Whilst this southern leg will provide us with shorter chainage than on earlier stages of the challenge, we’re running in and round what’s arguably probably the most busiest portions of London,” he mentioned. “As an example, we are facing the problem of negotiating an exceptionally advanced interface, together with the crossing of Euston Street with the 1000mm water diversion, whilst keeping up appropriate get right of entry to for visitors always.

“We will be able to be drawing at the revel in of the stipulations won at the earlier stages of this challenge and on our shut running dating with the major software house owners Thames Water, Cadent and LUL (London Underground), to make certain that we once more ship a first class end result to pave the best way for the brand new HS2 station’s building.”
Barhale additionally continues to ship enabling works via Hampstead Street, Cardington Boulevard and at Cumberland Marketplace in conjunction with the southern tie-in.
Faherty added: “This ultimate primary bundle of utilities works represents a key piece of the jigsaw in making ready Euston for HS2, and the entire group is proud to be taking part in a component.”
Design paintings for the utilities paintings is predicted to start out sooner than the top of summer time 2025 with building anticipated to be underway from March 2026. Crowning glory is predicted in early 2029.