Mammoet, the Dutch heavylift and particular shipping corporate has finished the relocation of the enduring Kiruna Church, considered one in all Sweden’s maximum precious architectural landmarks.
Greater than 1,000 hours of making plans went into the operation, which came about over two days.
Constructed within the early twentieth century and as soon as voted Sweden’s most pretty construction, Kiruna Church is among the nation’s greatest picket buildings. It needed to be moved (or demolished) because of the growth of Kiruna’s mine, which required a number of structures to be moved to a newly evolved town centre 5km away.
The Kiruna mine is the sector’s greatest underground iron ore mine. It’s owned and operated via LKAB – Luossavaara-Kiirunavaara Aktiebolag – the Swedish state-owned mining corporate.
Mammoet used to be commissioned via LKAB and its civil engineering contractor Veidekke to move the 713-tonne picket church in a single piece. The transfer, dubbed “The Nice Church Stroll,” drew hundreds of spectators, together with the King of Sweden.
Mammoet labored with Veidekke and Swedish picket engineering consultants to style and check the construction’s reaction to lifting and shipping. The operation used to be timed for August to steer clear of hostile climate prerequisites that might jeopardize the transfer.
The church used to be jacked as much as a top of one.3 metres and put on metal beams supported via two trains of 28 axle traces of self-propelled modular transporters (SPMTs). Mammoet’s customized tracking gadget ensured the construction remained strong all through the adventure, taking into consideration a most tilt of simply 75 mm between aspects.
Course arrangements incorporated brief street widening and compacting paintings, with trying out the use of SPMTs loaded with counterweights to simulate the church’s axle load.
The relocation came about right through sunlight hours on nineteenth and twentieth August 2025, with the church arriving safely at its new location. As soon as in position, the SPMTs reduced the construction onto its new concrete foundations.

Within the coming days, Mammoet may also relocate the church’s 90-tonne belfry the use of a unique SPMT configuration.
“This challenge exemplifies the significance of detailed engineering and making plans in executing distinctive and significant strikes,” stated Mammoet challenge supervisor William Soeters. “We’re proud to have performed a key function in safeguarding this historical construction for long term generations.”
Were given a tale? E mail information@theconstructionindex.co.united kingdom